Monthly Site Reporting: What to Look For

In short

How to read monthly site reporting so that receiving it is worth anything. Status is a lagging indicator: by the time a programme shows a task as late, the cause is one to three months old. The three trends that precede a delay are a trade slipping slightly and repeatedly, open queries accumulating faster than they close, and long-lead items still unconfirmed past their order date. It sets out what a useful report contains, how long-lead items are scheduled backwards from the day they are needed, and the questions worth asking every month.

In this article

Status is a lagging indicator

By the time a programme shows a task as late, the cause is one to three months old. The signal was in the trend.

A monthly report that says every trade is "on track" is not good news or bad news. It is a snapshot of where the work is today, and today was decided some time ago. What a client can still change is next quarter, and next quarter shows up in the patterns, not in the status column.

What a useful monthly report contains

  • Progress against the programme, trade by trade, with the percentage complete last month beside this month's.
  • Photographs from the same positions every month, so change can be seen rather than described.
  • Open queries — to the architect, the engineer, the authorities — with the date each was raised.
  • The long-lead schedule: every item, its order date, and whether it has been ordered.
  • Decisions the client owes, and the date after which each starts to cost time.
  • Cost: variations instructed this month, and the running position against the locked budget.

A report missing the last three is a progress report, not a programme report.

The three patterns worth watching

A trade slipping slightly, repeatedly. Any single month's shortfall is noise; three in a row is a resourcing problem that has not been named yet.

Open queries accumulating faster than they close. Every unanswered question is a piece of work that cannot start. When the count rises month on month, the site is about to start waiting on the drawings.

Long-lead items unconfirmed past their order date. This is the one that is easiest to see and most often ignored, because nothing on site looks wrong yet.

Why long-lead items are decided at month eight, not month twenty

Some things are not bought when they are needed; they are bought when their lead time says they must be. Natural stone selected from a particular quarry, imported window and door systems, a lift, custom ironmongery, specialist joinery and large-format tiles are the usual examples in a landed house. Each has to be selected, sampled, approved, made and shipped before it arrives on site.

So the order date is worked backwards: from the day the item is needed, less the time to make and ship it, less the time to sample and approve it. On a programme of about two years, that puts many of the important decisions around the middle of the build — which is why the answer above says month eight. A stone still being chosen at month eight is installed late at month twenty, and the house waits for it, finished in every other respect.

The useful report shows the long-lead schedule every month, and the useful reader checks one thing on it: is any item past its order date without an order?

The questions worth asking every month

  • Which trade is behind, and is this the first month or the third?
  • How many queries are open, and how many were open last month?
  • Which long-lead items are due to be ordered in the next two months, and are the selections made?
  • What do you need from me, and by when?

Who should be reading it

Somebody whose job is the programme rather than the work. On a split contract that person often does not exist: the builder reports on the build, the designer on the drawings, and nobody reads the two together. On our projects one party holds the whole programme, and pattern-reading across monthly reporting is one of the five places AI sits in the process, precisely because it is a task people do badly, and inconsistently.

The Complete Landed Rebuild Guide sets the reporting in the context of the whole programme.

Key takeaways

  • Read for trends. Status is one to three months behind the cause.
  • Watch slipping trades, accumulating queries and unconfirmed long-lead items.
  • Long-lead items are scheduled backwards from the day they are needed on site.
  • A selection still open at month eight is a delay at month twenty.
  • Programme risk raised early is the only kind that can be acted on.

On this site

First published in the KAPA Journal, written with KAPA Design Collective, the practice that designs and builds our residences.

Published by TMB Development at tmbdevelopment.com/journal/site-reporting-what-to-look-for. Quoting a passage with a link back is welcome; republishing it is not — see the terms.

Your site will answer this differently.

Send us the address and we will tell you what it allows before anyone draws anything.